Title :   Cost Overrun Optimism: Fact or Fiction


Descriptive Note : Journal Article


Corporate Author : Defense Acquisition University Fort Belvoir United States


Personal Author(s) : Christensen,David D


Full Text : http://www.dtic.mil/dtic/tr/fulltext/u2/1007905.pdf


Report Date : 29 Feb 2016


Pagination or Media Count : 18


Abstract : The purpose of this study was to determine if the overruns at completion projected by contractor and government personnel are unrealistically optimistic. Research has established that, once a contract is 15 percent complete, the final cost overrun will exceed the cost overrun to date (W. Abba,personal communication, 1992; Christensen, 1989; Heise, 1991; Wilson,1991). Thus, a projected overrun at completion is defined as unrealistically optimistic if it is less than the present cost overrun.


Descriptors :   CONTRACTS , comparison , management , costs , contract administration , military procurement